Report Instalation
PT Ultra Prima Abadi Jombang

Schedule Project

No

JOB DESK

Start

End

Status

1.

Open case

16/7/22

16/7/22

Done

2.

Move machine

in the line

16/7/22

16/7/22

Done

3.

Assembling/

instal machine

17/7/22

18/7/22

Done

4.

Leveling

17/7/22

18/7/22

Done

5.

Wirring

18/7/22

19/7/22

Done

6.

Power up

19/7/22

19/7/22

Done

7.

Trial dry run

19/7/22

20/7/22

On Progress

8.

Trial Fine Tuning ,Validasi & Commisioning product No 1

20/7/22

-

On Progress

9.

Trial Fine Tuning ,Validasi & Commisioning product No 2

Waiting

-

-

10.

Trial Fine Tuning ,Validasi & Commisioning product No 3

Waiting

-

-

Indication Progress Installation

1. Open Case
Complate 100%
Date : 16 July 2022
Date : 18 July 2022
Check Spare parts MP
2. Move machine in the line
Complate 100%
3. Assembling
Complate 100%
Date : 17 July 2022
4. Leveling
Complate 100%
5. Wirring
Complate 100%
Date : 17 July 2022
Date : 18 July 2022
6. Power Up
Complate 100%
7. Trial dry run
Complate 100%
8. Trial Fine Tuning ,Validasi & Commisioning product No 1
On Progress 26%

Trial Dry Run

1 Videos
9. Trial Fine Tuning ,Validasi & Commisioning product No 2
On Progress 0%
10. Trial Fine Tuning ,Validasi & Commisioning product No 3
On Progress 0%