Report Instalation
PT Tata Nutrisana

Schedule Project

No

JOB DESK

Start

End

1.

Open case

30/6/22

31/6/22

2.

Move machine

in the line

30/6/22

04/7/22

3.

Assembling/

instal machine

05/7/22

07/7/22

4.

Leveling

06/7/22

08/7/22

5.

Wirring

11/7/22

13/7/22

6.

Power up

14/7/22

14/7/22

7.

Trial dry run

15/7/22

18/7/22

8.

Trial Fine Tuning ,Validasi & Commisioning 4 hr product No 1

25/07/22

9.

Trial Fine Tuning ,Validasi & product No 2

10.

Trial Fine Tuning ,Validasi & Commisioning 4 hr product No 3

11.

Trial Fine Tuning ,Validasi & product No 4

12.

Trial Fine Tuning ,Validasi & Commisioning 4 hr product No 5

13.

Trial Fine Tuning ,Validasi & Commisioning 4 hr product No 6

14.

Trial Fine Tuning ,Validasi & product No 7

15.

Trial Fine Tuning ,Validasi & product No 8

Indication Progress Installation

1. Open Case
Complate 100%
Date : 30 June 2022
Date : 01 July 2022
Check Spare parts and Manual book
2. Move machine in the line
Complate 100%
3. Assembling/ Instal
Complate 100%
Date : 30 June 2022
4. Leveling
Complate 100%
Date : 01 July 2022
5. Wirring
Complate 100%
Date : 01 July 2022
Date : 04 July 2022
Date : 05 July 2022
6. Power Up
Complate 100%
Date : 05 July 2022
7. Trial dry run
Complate 100%
Date : 05 - 08 July 2022
Note : For Trial Dry Run Finish, after this we waiting next schedule from Tata Nutrisana side, Thank you very much